- Back to Education and Resources Watch the process! We will be continually updating this page with current photos of progress made - keep checking in to watch restoration in progress! ~
ABOVE: July 29th and 30th 2008 -- large debris piles are all that remains of the five old buildings ~ debris will be chipped...
Prep work continues, above. TOP: Project Manager Rebecca Benjamin stands in front of piled debris... ABOVE: Logs left from clearing site.
ABOVE: Trench being dug for de-watering site prior to excavation...
Above: Digging test pits to check water levels near berm...
Above: The pile of fill, loading into trucks for composting...
Above: Two cranes used to fill chipper -- chipping all old building material, as well as trees removed from site - chips used to create site access road...
Above: Excavation of fill revealed old historic tidal channels! These were excavated out - see resulting channel already filling with tidal waters ...
Above: Wider view of newly excavated historic channels...
Above: Work underway, fill removal and transport... MORE TO COME > > > |
Visit the Salmon Estuary blog site by clicking HERE -- to view updates, pictures, videos, news articles, and more! Salmon ~ Snow Creek After several years of planning by our project partners, and tremendous financial support from our funding sources, the work has started!... Seton Construction has cleared the sites in preparation for excavation. Trees and buildings were removed at the end of July. They have excavated trenches around project footprints to de-water the areas prior to fill removal... If you have questions, feel free to contact Rebecca Benjamin at North Olympic Salmon Coalition - (360) 379-8051 |